Mexico Lags LatAm Data-Center Boom With 71 Sites to Brazil's 225
TL;DR
- Mexico hosts just 71 of Latin America's 500-plus data centers, against 225 in Brazil, despite nearshoring tailwinds.
- An electricity connection contract takes at least eight months in Mexico and up to three years, per CloudHQ's country head Luis Lugo.
- MEXDC still expects just over $20 billion of direct data-center investment over the next four years, concentrated in an already-saturated Querétaro.
Mexico hosts 71 of Latin America's more than 500 data centers, against 225 in Brazil, Bloomberg reports. The constraint is not demand. It is the grid and the permit stack.
CloudHQ has a $4.8 billion plan for six data centers in Querétaro, the state that holds about 70% of Mexico's existing capacity, including sites run by Amazon Web Services and Google. The company has applied for roughly 111 permits, not counting energy ones. "It takes at least eight months under normal circumstances to get an electricity connection contract," Luis Lugo, CloudHQ's top executive in Mexico, told Bloomberg. In harder cases, Lugo said, the wait can run to three years.
Querétaro is already straining under what it has. In El Marques, a small town in the state, authorities are now scheduling power cuts just to keep the system from collapsing.
Economy Minister Marcelo Ebrard has said companies have announced plans to invest more than $8 billion in Mexican data center projects, with some developers building their own power plants and lines to get around the utility queue. The Mexican Data Center Association, MEXDC, expects just over $20 billion of direct investment over the next four years. That forecast sits against a backdrop in which AI Weekly has logged 489 AI-infrastructure alerts in the last 90 days, most of the capital landing in grids that can actually plug it in.
Originally reported by bloomberg.com