JERA Pitches Anthropic, Meta on Data Centers Beside Power Plants
TL;DR
- JERA is in exploratory talks with Anthropic, Meta, Amazon, Microsoft and Google to colocate AI data centers at its Tokyo-area thermal power plants.
- An October 1 MoU with Dell Technologies and UK firm Rhaelm targets a 400 MW behind-the-meter AI facility at the Chiba plant, operational by 2028.
- JERA operates more than 20 thermal plants with a combined capacity of almost 55 GW, letting hyperscalers skip years of grid-upgrade waits.
Japan's largest power producer is pitching its thermal plants as data-center real estate. JERA has entered exploratory talks with Anthropic, Meta, Amazon, Microsoft and Google to build behind-the-meter AI data centers next to its power stations around Tokyo, Nikkei Asia reported.
The blueprint is already on paper.
On October 1, JERA, Dell Technologies and UK firm Rhaelm signed a memorandum for a 400-megawatt-class AI data center on land next to the Chiba thermal plant, with phased operations targeted for 2028. Total investment is expected to exceed $15 billion, about 2.3 trillion yen, across land, power infrastructure, construction and AI compute. JERA currently runs more than 20 thermal power plants with an estimated combined capacity of almost 55 GW, and Apollo Global Management is backing Rhaelm as a strategic investor.
Yukio Kani, JERA's Global CEO and Chairman, says the company's LNG value chain gives AI infrastructure 'access to the large-scale, reliable energy it needs.' The pitch to hyperscalers is time: colocating directly next to generation lets a buyer draw electricity straight from the plant rather than wait years for high-voltage transmission upgrades, DatacenterDynamics reported.
Neither Anthropic nor Meta has publicly confirmed the negotiations, and no formal agreement with any of the hyperscalers has been signed. The story sits next to our coverage of a draft Japanese AI law that would allow on-site inspections of OpenAI and Anthropic, the same labs JERA is courting as power customers.
Originally reported by asia.nikkei.com
Read the original article →Original headline: Jera Opens Talks With Anthropic, Meta for Behind-the-Meter Data Centers Across Tokyo Area